It's summer and that means one thing on the DL, trackwork season. Taken from the GVT yahoo group: Have learned that several maintenance projects will soon be
undertaken by the D-L:
1. 3000 ties between MP-101-96
2. 2900 ties between MP 78-74 (Water Gap)
3. 2900 feet of rail change-out MP 74-78
4. 4 miles of re-surfacing MP 74-78
5. Crossing replacement & surface N Courtland St, E. Stroudsburg
6. Ties at mall siding Steamtown
7. Double end Tobyhanna Siding & rehab old west leg of wye for
propane storage.
This will mean late-running PT-98's and 97's
undertaken by the D-L:
1. 3000 ties between MP-101-96
2. 2900 ties between MP 78-74 (Water Gap)
3. 2900 feet of rail change-out MP 74-78
4. 4 miles of re-surfacing MP 74-78
5. Crossing replacement & surface N Courtland St, E. Stroudsburg
6. Ties at mall siding Steamtown
7. Double end Tobyhanna Siding & rehab old west leg of wye for
propane storage.
This will mean late-running PT-98's and 97's
Nick