by HSSRAIL
A few comments on this.
NS and CPR are not antagonistic rivals but partners. The NS and CPR are working closely together on the D&H. The D&H's physical plant is creating more friction than anything else capacity is very tight on this corridor.
Insofar as getting freight trains around the catenary the CNJ right away runs parallel through downtown Dover by reactivating this right of way and swinging onto it west of the Catenary you can than bypass Dover Station and build another track on the North Side of the line to Denville and head towards Boonton on the North side of the tracks. NJ Transit trains leave the Boonton Line at Mountain View and the right of way to route 80 is still there. Placing Railroad tracks in highway rights of way are not without precedent. Chicago has done it very successfully. According to Tabor the right of way of route 80 is wide enough to accomodate a single track. The cost of building a right of way to route freight via the cut-off makes it impractical but, the concept in of itself to run freight via Lackawanna is not. Total amount of new track that would have to be layed
is as follows:
1 1/2 miles through Dover and construction of one control point west of Dover Station.
2 miles of track along the northside of the existing NJT route to Denville.
13 miles of track or capacity upgrade on the NJT route between Denville and Mountain View.
Use of existing track Mountain View to End of Track Totawa.
4 miles new track along route 80 to NJT Mainline in Paterson. New control point in Paterson.
Control points cost 1 million dollars to make.
2 million to install the junctions.
Track costs 1 million per mile. $20 million dollars for track improvements
Total cost for the project probably in the $23 million dollar range I tacked on a million plus for studies. Not likely that New Jersey or NS and CP Rail would want to do this as this project is not cost effective. Things change with time, if the war in Iraq and the instability in Iraq was to engulf the entire middle east gas could go to $20 a gallon.. What is practical now and what is practical in the future can certainly change with time. If gas prices shot up to the magnitutes I just stated the cut-off project becomes an immediate go.
I agree freight on the cut-off now is impractical whether that continues to hold is something that remains to be seen with time. Non of the problems mentioned on routing freight via the cut-off are unsolvable they are currently impractical.
NS and CPR are not antagonistic rivals but partners. The NS and CPR are working closely together on the D&H. The D&H's physical plant is creating more friction than anything else capacity is very tight on this corridor.
Insofar as getting freight trains around the catenary the CNJ right away runs parallel through downtown Dover by reactivating this right of way and swinging onto it west of the Catenary you can than bypass Dover Station and build another track on the North Side of the line to Denville and head towards Boonton on the North side of the tracks. NJ Transit trains leave the Boonton Line at Mountain View and the right of way to route 80 is still there. Placing Railroad tracks in highway rights of way are not without precedent. Chicago has done it very successfully. According to Tabor the right of way of route 80 is wide enough to accomodate a single track. The cost of building a right of way to route freight via the cut-off makes it impractical but, the concept in of itself to run freight via Lackawanna is not. Total amount of new track that would have to be layed
is as follows:
1 1/2 miles through Dover and construction of one control point west of Dover Station.
2 miles of track along the northside of the existing NJT route to Denville.
13 miles of track or capacity upgrade on the NJT route between Denville and Mountain View.
Use of existing track Mountain View to End of Track Totawa.
4 miles new track along route 80 to NJT Mainline in Paterson. New control point in Paterson.
Control points cost 1 million dollars to make.
2 million to install the junctions.
Track costs 1 million per mile. $20 million dollars for track improvements
Total cost for the project probably in the $23 million dollar range I tacked on a million plus for studies. Not likely that New Jersey or NS and CP Rail would want to do this as this project is not cost effective. Things change with time, if the war in Iraq and the instability in Iraq was to engulf the entire middle east gas could go to $20 a gallon.. What is practical now and what is practical in the future can certainly change with time. If gas prices shot up to the magnitutes I just stated the cut-off project becomes an immediate go.
I agree freight on the cut-off now is impractical whether that continues to hold is something that remains to be seen with time. Non of the problems mentioned on routing freight via the cut-off are unsolvable they are currently impractical.
HSS