Some good news about the progress on 18. A successful hydro test was performed on the boiler. This passed indicating no major problems on what was repaired. The cab has been rehung and now crews are working on reinstalling piping and air valves.
I can't give any estimate as to a return to regular service, but I'd wage a guess that if all goes well, it could be next seasong. I wouldn't expect it opening day as there are still a lot of hurdles to get over.
Work done to date include side firebox sheets replaced, about 40-50% of all stays renewed, front and rear tube sheets, new flews installed, major smoke box patches, all new nozzle and draft components installed, new pilot beam, front pony truck and stearing assembly rebuilt and installed, some sring suspension work. As piping and components get reinstalled, everything will have to be inspected and another hydro passed after final reassembly. Air compressors are being rebuilt (or have been and are awaiting delivery). The tender will still need attention prior to return to service. This includes one axle replaced, minor side sheet repair, good cleaning and interior painting.
Though it isn't what some are looking for as far as a date for return to service, at least it is a good step forward in reassembling it.
I can't give any estimate as to a return to regular service, but I'd wage a guess that if all goes well, it could be next seasong. I wouldn't expect it opening day as there are still a lot of hurdles to get over.
Work done to date include side firebox sheets replaced, about 40-50% of all stays renewed, front and rear tube sheets, new flews installed, major smoke box patches, all new nozzle and draft components installed, new pilot beam, front pony truck and stearing assembly rebuilt and installed, some sring suspension work. As piping and components get reinstalled, everything will have to be inspected and another hydro passed after final reassembly. Air compressors are being rebuilt (or have been and are awaiting delivery). The tender will still need attention prior to return to service. This includes one axle replaced, minor side sheet repair, good cleaning and interior painting.
Though it isn't what some are looking for as far as a date for return to service, at least it is a good step forward in reassembling it.