by Sand Box John
Safety issue lurks under Dulles rail bridge plan
Federal transit agency investigates delay in testing foundations built in 1977
By Lisa Rein
Washington Post Staff Writer
Sunday, November 22, 2009
Tracy A Woodward The Washington Post
A question of safety
(graph showing the location of the column foundation footings)
I have made it know for many years in this forum and others of the existence of the provision built in the K Route Orange line easement to accommodate the construction of the future Tyson, Dulles, Loudoun County N Route Silver line.
I don't see this being all that big of an issue. These footing, when originally built, were designed to WMATA's established loading standards. They have sat unused for more then 30 years. During those 30 years they have not been subjected to the pounding of weight from passing trains. WMATA has hundreds of similar pier footings throughout the system that are older that have never failed. Those older footing have been carrying the load of trains a hell of a lot longer then these that have not.
I am not buying the electrolysis induced corrosion argument. The folks that designed and built the system were very meticulous about bonding and ground their structures to minimize electrolysis induced corrosion. VDOT, MDSHA and DCDPW have numinous bridge foundation structures adjacent to WMATA's tracks that have not suffered from electrolysis induced corrosion.
The article mention that WMATA could not locate any of the records or documents on the foundation footing. Did they think to check VDOT plan and record archive? The article mentions that it was a contractor working for VDOT that did the construction of the column foundation footings.
I have been aware of the column stub between tracks K3 and K1 as seen in the photos above sense before the K Route Orange line opened to Vienna in on 06 07 1086.
What I didn't know is there were 12 other foundation footing constructed at the same time column stub was built.
The alignment shown in the FEIS did not utilize any of the column foundation footings. There is no mention in the FEIS for the reason why the column foundation footings were not to be utilized.
Federal transit agency investigates delay in testing foundations built in 1977
By Lisa Rein
Washington Post Staff Writer
Sunday, November 22, 2009
Tracy A Woodward The Washington Post
A question of safety
(graph showing the location of the column foundation footings)
I have made it know for many years in this forum and others of the existence of the provision built in the K Route Orange line easement to accommodate the construction of the future Tyson, Dulles, Loudoun County N Route Silver line.
I don't see this being all that big of an issue. These footing, when originally built, were designed to WMATA's established loading standards. They have sat unused for more then 30 years. During those 30 years they have not been subjected to the pounding of weight from passing trains. WMATA has hundreds of similar pier footings throughout the system that are older that have never failed. Those older footing have been carrying the load of trains a hell of a lot longer then these that have not.
I am not buying the electrolysis induced corrosion argument. The folks that designed and built the system were very meticulous about bonding and ground their structures to minimize electrolysis induced corrosion. VDOT, MDSHA and DCDPW have numinous bridge foundation structures adjacent to WMATA's tracks that have not suffered from electrolysis induced corrosion.
The article mention that WMATA could not locate any of the records or documents on the foundation footing. Did they think to check VDOT plan and record archive? The article mentions that it was a contractor working for VDOT that did the construction of the column foundation footings.
I have been aware of the column stub between tracks K3 and K1 as seen in the photos above sense before the K Route Orange line opened to Vienna in on 06 07 1086.
What I didn't know is there were 12 other foundation footing constructed at the same time column stub was built.
The alignment shown in the FEIS did not utilize any of the column foundation footings. There is no mention in the FEIS for the reason why the column foundation footings were not to be utilized.
John in the sand box of Maryland's eastern shore.