First up, the Amtrak Vermont is slated to make another attempted return on Friday, August 12 with the northbound #56 run. Both north and southbound trains will run through August 17, when on the 17th, only the southbound #55 will operate. That is all contingent on timing over the slow-order trackage that exists due to the project. The last attempt to run the trains on July 22, resulted in more than 4 hours of slow orders and the train was halted at White River Jct. That stretch of 6 days was then covered by buses. Bustitution will return on August 17 with the northbound run and run through September 1, when the train is to return for the next 6-day block. Significant progress has been made in reducing the slow orders created by the new rail installation, however many still do exist.
The operation of Amtrak coincides with the work gangs 6-day rest period. The Atlas Rail Gang had reached the end of available (on hand) rail to install last week and over last weekend, reinstalled (with 'relay' 115-pound stick rail) the White River Jct. siding. For those who aren't familiar with the project, the Atlas Rail gang was doing the east rail, while RailWorks was installing the west rail. That said, Atlas finished out the available welded rail at mile 155 of the Palmer Subdivision, roughly Charlestown, NH, before going back to do the WRJ siding. They then took on a variety of finishing projects north of White River Jct., before ending today. The RailWorks rail gang was shipped back north on the Roxbury Sub to the Randolph area to work on gauging from mile 48 south to Windsor, VT (mile 0 of Roxbury Sub).
Rail Train #16 arrived ahead of Rail Train #15, as #16 has 136-pound rail destined for the stretch around Bellows Falls. 136-pound sections had already been delivered on Rail Train #13 and were dropped from north of the Connecticut River bridge in North Walpole, NH to the Bellows Falls Tunnel for the new redesigned interchange and diamond crossing area with the Vermont Rail System there. With Rail Train #16 on the property, the RailWorks CWR Laying Gang will join up with the LB Foster Rep for laying rail south from mile 155 on the Palmer Sub this weekend. Rail Train #15 is slated to be on the property on Friday or Saturday, but will be staged in St. Albans or Brattleboro, pending availability of the installation crews off Rail Train #16. Rail Train #17 will be released and shipped from the SDI Columbia City, IN mill on August 16, while Rail Train #18 (the final rail train for the project) is tentatively slated to be shipped on September 6.
Rail Train #16 rolls toward Windsor, VT on August 10, 2011.
Unitrac is busy picking up the OTM (rail and old spikes, anchors, plates, etc.) and relay rails south of Claremont Jct., NH toward the end of the current completed portion. More work will exist for them after the install gangs get the next 7+ miles of rail installed from Rail Train #16. Unitrac had been staged at White River Jct. for sorting and car loading, however that operation has temporarily been or will be shortly moved to the north end of Claremont Jct. adjacent to the siding.
The RailWorks tie gang is working south from Roxbury, VT and continues to work at steady pace. C&G Surfacing is right behind them and had worked south of the Montpelier Jct., VT area earlier this week. The RailWorks tie removal/salvage gang is working south from Milton, VT retrieving the discarded ties for disposal. Of note, ties may not be inherited by a private individual, whether by 'permission' or by sale. RailAmerica has strict liability rules and is selling most of the ties to the large Pennsylvania Koppers Co-Gen power plant. Also in the Montpelier Jct. area is the RJ Corman Construction crews responsible for the building and installation of the new high speed siding switches.
Other contractors are as follows:
- Atlas Bridge is working on Bridge 33.75 on the Roxbury Sub
- RailWorks Bridge is working on Bridge 33.57 on the Roxbury Sub
- Balfour Beatty is upgrading and replacing crossing protection signals at mile 46 on the Roxbury Sub
- ECI Rail is working on the upgraded CTC system that will be in place south from White River Jct. to East Northfield
The project is shaping up as follows 8/5:
- Rail Installation (Atlas/RailWorks combined) is at 74.85% complete
- 2011 Tie Installation is at 44.85% complete
- 2011 Surfacing is at 37.46% complete
- 2011 Suface Ballasting is at 32.14% complete
- Turnout installation is at 15% complete
- Public Crossings 34.09% complete
- Private Crossings 42.86% complete
- Bridge work is 30% complete
- Signal work is collectively near complete