David wrote:The bridge in Collings Lakes has been repaired. There has been some clearing of the line from Winslow Junction to Vineland. There has been some legal problems that is holding up return to service on this segment. The service ended over the line in the late 90s when the bridge collapsed. From what I understand, from my brother, is the bridge was completed but looks rough.
Bridge work is complete, the bridge is OK but not constructed completely to SRNJ specs. Apparently W.M. Brode (major bridge construction company, they've done thousands of bridges) managed to make a mistake in the structural physics for construction...they actually constructed the approaches to the bridge 2 feet too high! Don't ask how they managed to do that...
SRNJ ran a test train (actually just a light engine) over the bridge from Winslow on Friday, October 29th, with the bridge constructed improperly...it looks good, with the exception of the approaches, which should be repaired soon...
In theory, I believe SRNJ could have trains up and running between Winslow and Vineland by the end of the year, but the line is pretty bad, might take longer to clear all that brush out...it's amazing what can grow up in 5 years...
I'm going to try to get down that way on Saturday, if I can get some time, I'll see what's going on. I'll come back with pics for everyone to see, if I do get down there...