apodino wrote: ↑Thu Jun 11, 2020 1:01 pm Remember that the Lechmere viaduct is being demolished and rebuilt as far south as the Gilmore Bridge.I didn't know that, which explains why it will take a year to complete.
Welders are using blow torches to cut the supports and then a crane lowers it to the ground.
As for the shuttle buses, why not just extend the bus routes that terminate at Lechmere and have them terminate at North Station instead. There is a dedicated bus lane. If they don't want to extend all four bus routes, perhaps extend the 87 & 88 as they alternate every 10 minutes to/from Lechmere.
Attachments:
200613_140605_CuttingLechmereElevated.jpg (129.62 KiB) Viewed 3156 times
200613_140811_LechmereElevatedRemoval.jpg (99.08 KiB) Viewed 3156 times