by johnhenry
Here is a map (if I did this right) I got a year ago relating to the track by the reservoir.
You do not have the required permissions to view the files attached to this post.
Railroad Forums
Moderator: MEC407
bostontrainguy wrote: ↑Wed Aug 03, 2022 7:43 am Note that some of this is going to be double track since switch panels have been dropped in at least two spots.Nope, simply replacing the old ones.
F74265A wrote: ↑Wed Aug 03, 2022 9:30 am I don’t anticipate any double trackI see reports of new switch panels dropped at New Bond Street. There is no existing siding here. This would seem a good place for the start of a second track but I don't know anything more than you do. They are parking and fueling trains at this spot now. It will be interesting to see what happens here.
Switch panels have been reported near the locations of existing short sidings in Clinton and Worcester