Line segment still shutdown today. Supposed to be open Monday. http://wmata.com/about_metro/news/Press ... aseID=6144.
The press release mentions the following repairs are required:
*Replacing about 200 feet of running rail
*Rebuilding 150 feet of electrified third rail
*Replacement of two track crossings at the interlocking
*Removal and replacement of approximately 200 wooden cross ties that hold the rail in place