 #1485686  by Bill Reidy
 
In its day the Woods Hole branch saw 50-mph passenger trains and heavy wartime traffic to Camp Edwards. That the New Haven standard 107-lb rail has held up well all these years is a tribute to the New Haven's track maintenance back in the day.
 #1485760  by Falmouth Secondary to Otis
 
The Falmouth secondary is in the planning stages for rehabilitation per MassDOT CIP State Rail plan. The Otis Industrial track is to be evaluated for rehabilitation as well to better serve the Military & the reopened UCRTS station, along with other future use's of the line such as establishing a regional salt supply depot.
 #1490187  by Falmouth Secondary to Otis
 
Today Northern Construction started staging construction supplies next to the Barlow's Landing RR crossing in Pocasset, MA to replace water culverts between the Pocasset river RR trestle and Monk's Park area on the Falmouth secondary line. Will be watching progress as RR line is active with C&D being shipped from transfer station on Joint base Cape Cod.
 #1490338  by ANRP2
 
Falmouth Secondary to Otis wrote:From what I have seen walking along the Falmouth secondary line all I have found are 107 lb rails dated 1915
Is it necessary to upgrade this rail to meet military preparedness requirements?
 #1490340  by Safetee
 
I don't know what the military requires for rail these days. However, the rail currently in use on the base trackage is so bad that I think they'd have an awfully hard time claiming that the 107 on the Falmouth wasn't up to their combat ready standards.
 #1490393  by Falmouth Secondary to Otis
 
From what I have read locally the Military is planning some equipment moves in the next year or two. The Otis Industrial track spur is to be under study by MassDOT to be rehabilitated according to the 2018 Mass State Rail plan with new ties and ballast. Also the Falmouth secondary line is in the planning stages for ties / ballast / crossing upgrades and also culvert replacements which started this past Monday. In the past the Military shipped tanks / trucks / various other equipment & supplies which resulted in most of the bridges being replaced on the Falmouth secondary line in the mid 1980's due too crumbling bridge abutments dropping concrete chunks on the road below when the fully loaded train would pass.
Last edited by MEC407 on Wed Nov 07, 2018 2:10 pm, edited 1 time in total. Reason: unnecessary quoting
 #1490403  by Falmouth Secondary to Otis
 
Culvert replacement on Falmouth Secondary line underway in Pocasset, MA by Monk's Park area
Attachments:
Area on the inlet side
Area on the inlet side
DSCF2433.JPG (1.64 MiB) Viewed 3371 times
Area being prepared for culvert replacement on the harbor side
Area being prepared for culvert replacement on the harbor side
DSCF2429.JPG (1.52 MiB) Viewed 3371 times
 #1490625  by Falmouth Secondary to Otis
 
Mass Coastal delivered 8 empty C&D cars to UCRTS on Otis today and picked up all there full cars as the Falmouth Secondary is being shut down for about a week. A 36" culvert is being replaced under the RR tracks along with some repairs to the tracks and causeway by Monk's Park in Pocasset, MA
Attachments:
Mass Coastal crossing culvert /causeway area to be repaired
Mass Coastal crossing culvert /causeway area to be repaired
DSCF2452.JPG (1.67 MiB) Viewed 3265 times
 #1490779  by Falmouth Secondary to Otis
 
Falmouth Secondary line culvert excavation is underway with supplies being railed down to Monk's park area site from Barlow's landing RR crossing staging area in Pocasset, MA
Attachments:
Culvert excavation underway 11/10/2018
Culvert excavation underway 11/10/2018
DSCF2464.JPG (1.54 MiB) Viewed 3176 times
Barlow's landing RR crossing staging area 11/10/2018
Barlow's landing RR crossing staging area 11/10/2018
DSCF2469.JPG (1.69 MiB) Viewed 3176 times
 #1491533  by Falmouth Secondary to Otis
 
Culvert replacement on Falmouth Secondary line in Pocasset, MA is completed with MOW track work being done today to restore the line to active status so Mass Coastal can pick up full cars of C&D from the Otis transfer station.
Attachments:
MOW equipment finishing up track work on causeway /culvert project area
MOW equipment finishing up track work on causeway /culvert project area
DSCF2483.JPG (1.58 MiB) Viewed 2998 times
Culvert under RR tracks completed
Culvert under RR tracks completed
DSCF2480.JPG (1.52 MiB) Viewed 2998 times
 #1491542  by malbojah
 
Do you think the culvert replacement took into thought the possible connection of the bike trails and left enough room for a bridge to piggyback the rail line?