The Metropolitan Transportation Authority (MTA) just sent us its plan for what it will do if the storm that's predicted to basically be the storm to end all storms hits New York City.
For now, the MTA is suspending construction on almost all subway construction projects it had planned for the weekend, with the exception of work planned for the 7 and J lines. Those projects are planned to conclude before the "Frankenstorm" is expected to hit the Big Apple on Sunday.
As is currently the plan, there will be no shutdown of services in advance of the storm, but officials say there will be if the storm's winds top 39 mph.
The rest of the MTA's plan for the storm is as follows:
...
New York City Transit
Most scheduled weekend subway service changes for construction projects have been cancelled, with the exception of changes planned for the 7 and J lines, which are now scheduled through Saturday only. Crews are inspecting and clearing main drains and pump rooms throughout the subway system. Personnel are checking and cleaning all known flood-prone locations and these areas will continue to be monitored.
Extra workers and managers are prepared to staff New York City Transit's Incident Command Center, situation room, satellite desks, depot operations and facility operations as necessary. The Incident Command Center will be activated starting at 8 a.m. Sunday. Among those present in the ICC throughout the duration of the storm will be Customer Advocates, who will ensure that all decisions made during the event will reflect a focus on customers. They fill a position created after reviews of the agency's performance during Tropical Storm Irene.
Trains will be removed from outdoor yards prone to flooding and moved to more secure locations. Subway ventilation grates vulnerable to flooding will be sandbagged and tarped over. Many station entrances and ventilation grates in low-lying areas have been successfully modified in recent years to raise them above street level, making it more difficult for floodwaters to enter the system.
All portable pumps and emergency response vehicles will be checked, fueled and made ready for service. Outside contractors have been asked to prepare their work sites for heavy weather.
Bus operators are ready to move buses that normally park in low-lying depots to areas of higher ground.
Next stop, Willoughby
~el Jefe :: RAILROAD.NET Site Administrator/Co-Owner; Carman at Naugatuck Railroad
YouTube Instagram Facebook
~el Jefe :: RAILROAD.NET Site Administrator/Co-Owner; Carman at Naugatuck Railroad
YouTube Instagram Facebook