  • Progress of Train de l'Est - AMT Montreal

  • Pertaining to all railroading subjects, past and present, in Canada. For specific railroad questions, see Fallen Flags and Active Railroads categories.
Pertaining to all railroading subjects, past and present, in Canada. For specific railroad questions, see Fallen Flags and Active Railroads categories.

Moderator: Ken V

 #1167521  by sparkyhero
 
Hi,
This topic concerns the progress of AMT's Repentigny-Mascouche Line, also called Train de l'Est, set to begin operations in Spring of 2014.
In the latest news, 66% of the Train de l'Est was completed. Does someone have any further information concerning the advancement of the project?
 #1167533  by sparkyhero
 
In the latest news:
Ahuntsic Station: there are pillars to support the platform, but no further work has been done. Construction of the main building hasn't begun yet.
Anjou Station: 90% completed.
Mascouche Station: construction has begun in July 2012. No further information.
Saint-Michel Station: construction is set to begin in 2013. No further information.
Pointe-aux-Trembles Station: construction is set to begin in 2013. No further information.
Repentigny Station: construction has begun in August 2011. Several structures are slowly being built. No further information.
Rivière-des-Prairies Station: construction hasn't begun yet. The construction contract is pending right now. Construction should begin in June or July of 2013.
Sauvé Station: the pillars to support the platform have been installed. Construction has begun in 2010. No further information.
Saint-Léonard Station: the main building is being built. Estimation of completion would be superior to 75%.
Terrebonne Station: construction has begun in October 2012 and should be completed soon. No further information.
Highway 640: construction seems to be going well. Estimation of completion would be superior to 75%
Eastern Junction: construction seems to be going well. Estimation of completion would be superior to 75%.