There are two new documents in the library section of the Gateway tunnel website:
http://www.hudsontunnelproject.com/docu ... ebsite.pdf
http://www.hudsontunnelproject.com/docu ... ebsite.pdf
I will summarize the major items from them that were new to me at least, maybe others were aware of them already.
1. Geotechnical boring is going on at the Wheehawken vent plant site now. It appears similar to the boring that I noted previously in the marshy area south of the approach tracks of the existing tunnels.
2. Preliminary environmental remediation of the Wheehawken site is planned for this fall(2018).
3. Most of the spoils removal will be through the North Bergen site because Wheehawken complained about truck traffic.
4. They will build 25 feet tall walls around the site for noise mitigation and also pay for new noise insulating windows for all neighboring residences.
5. Tunnel construction timeline is March 2019-December 2026. Surface track construction is March 2019-November 2023. Old tunnel rehabilitation is January 2027-December 2030.
6. Most construction including tunnel mining will occur between 7am and 11pm on weekdays only.
It is interesting that 2 above is implied as a done deal even though the full funding for the tunnel has not been secured yet. 3 and 4 illustrate the ways costs of these projects get out of hand because every property owner and local elected official needs to be bought out. I imagine every building owner in 2 block radius in New York will demand the same for the New York vent plant. 6 might be illustrative of union power -- why they cannot drill the tunnel 24/7 is beyond me. With multiple crews you would not need to pay anyone overtime(some people will work weekends and get days off during the week -- it happens in other industries all the time) and spoil removal and material trucking could still be only on weekdays. Aahh, the many ways to make this project incredibly expensive ... and to derail it ...