  by Disney Guy
 
The shoo fly track takes shape, with twin guard rails for added rigidity.

Electrical conduit tubes are stacked up at the far (Boston) end of the track, suggesting that temporary power feeder cables will be laid in this trackway.

As of 1/12/16 switch work on the existing tracks has not begun
You do not have the required permissions to view the files attached to this post.
  by Diverging Route
 
IMG_6614.JPG
Last night a track panel was laid on top of the stub end on the Cambridge side. Still no sign of curved track nor a turnout. Picture taken from my perch in Tower One.
You do not have the required permissions to view the files attached to this post.
  by MBTA3247
 
I saw a ballast tamper on the south end of the bridge today.
  by parovoz
 
I was on the outbound train today at around 4PM. The train took the new outer track. The old outbound track is firmly disconnected on both ends (no switches or anything). Surprisingly, the ballast tamper and another track maintenance car are stored on the disconnected track.
  by octr202
 
During the next closure(s) the inbound track will be swung over and connected to the former outbound track on the bridge, hence how the track equipment will be "liberated" from where they are.
  by The EGE
 
They must have gotten track work done last night. My outbound at 4pm yesterday crawled over the bridge, but 8am outbound today was at normal speed.
  by Diverging Route
 
IMG_6627.JPG
IMG_6626.JPG
Here's the view from Tower One today, with the temporary northbound track in service.
You do not have the required permissions to view the files attached to this post.
  by Disney Guy
 
A Cambridge bound train runs on the temporary track alongside Boston bound motorists. The motorists should already be accustomed to the Jersey barrier that has walled off the track area for several weeks. On Tuesday Oct. 19, inspectors (wearing yellow safety vests) have been riding some if not all trains over the bridge.
a6518.jpg
a6514a.jpg
A train has just left Charles Station and takes the temporary shoo fly track. The inbound track in the foreground will be connected to the old outbound track over the bridge which is the center track as shown. At least one driver announced a 10 MPH speed over the bridge which would have added two minutes to that portion of the trip. Station announcements mentioned "delay due to track work on the bridge."
You do not have the required permissions to view the files attached to this post.
  by parovoz
 
New alignment, as seen from Charles/MGH.
You do not have the required permissions to view the files attached to this post.
  by octr202
 
Yes, the announcement said that the planned weekend work could be completed overnight. They had originally scheduled one contingency weekend shutdown in case of weather delays.

The remaining work mainly involves finishing the construction barriers to separate the work area from the active tracks.

Looking forward, there's likely some sections near the north end of Charles/MGH that will be hard to work on while service is operating. It will be interesting to see if they can complete the work under this area solely on weekend shutdowns.
  by Diverging Route
 
IMG_7414.JPG
The view from Tower One today.

Note the pile of rail. I believe the schedule is for the new shoo-fly to be built starting next week.

The railbed for the future permanent Boston-bound (but temporary Cambridge-bound) track is nearly complete, and is being painted yellow today (anyone know why?). The shoo-fly will go upstream of this railbed for the upcoming Stage 4 of construction.

ETA: The yellow was just a primer. It's now painted gray.
You do not have the required permissions to view the files attached to this post.
  by Diverging Route
 
And now there's track going in on the new (permanent) inbound trackway (soon to become the temporary outbound trackway). As seen from Tower One.
You do not have the required permissions to view the files attached to this post.
  by Diverging Route
 
Today's view from Tower One. Just now, workers have drawn the line that will be the bound for the temporary Boston-bound shoo-fly track ROW. You can see it in the picture just above the two white trucks -- it's the one on a diagonal, with another one just above it that will be the temporary fence protecting the vehicle lane.

Also note that at least on the Cambridge end, the rail has been placed on the ties of the new permanent track.
You do not have the required permissions to view the files attached to this post.
  by Diverging Route
 
The new shoo-fly (temporary Boston-bound track) is mostly in-place now, though not connected on either end of the bridge.

When was the last time a Charles River bridge had four tracks :-D Grab your pictures now, it won't be that way for long! The switchover to the two upstream tracks and removal of the two downstream tracks will occur over the next month.