  • Guilford Rail System changed its name to Pan Am Railways in 2006. Discussion relating to the current operations of the Boston & Maine, the Maine Central, and the Springfield Terminal railroads (as well as the Delaware & Hudson while it was under Guilford control until 1988). Official site can be found here: PANAMRAILWAYS.COM.
Guilford Rail System changed its name to Pan Am Railways in 2006. Discussion relating to the current operations of the Boston & Maine, the Maine Central, and the Springfield Terminal railroads (as well as the Delaware & Hudson while it was under Guilford control until 1988). Official site can be found here: PANAMRAILWAYS.COM.

Moderator: MEC407

  by KSmitty
 
CPF363 wrote:Still 5 MPH speed limit through the derailment site. Roughly taking up to three hours to make the run from the Hill Yard to New Bond Street. Wonder if any of the track work that has been working on the Portsmouth Branch over the past few months will make their way to the Worcester Route before winter to pick up some of the slow speeds on the line.
Unless they have 2 tie gangs, not gonna happen for a while. Seems most of the gang's equipment thats been in use on D1 the last couple years is tied down in Winthrop, ME right now. A TRIPP or 2, couple Kershaws, spikers, spike pullers, etc...
  by Sprinter611
 
As of 6:00pm today, MEC 306 & 6 work hoppers are still on the siding at Clinton, MA. There is 2 grain hoppers separated from the extra on the siding too.