2nd Section.
The following annotated present-day aerial photo shows the relative locations of the lines of transportation.
4 West End 1995 USGS Aerial.jpg
As shown in the earlier 1906 map of the eastern connection of the U&MV and the WS, after leaving that connection the U&MV crossed the Mohawk River. Note that the street-running local trackage of the U&MV crossed the Mohawk River on its own bridge and RoW east (downstream) of the highway bridge(s), which were themselves east of the double-track U&MV by-pass bridge.
6 East End 1905 Pre-Barge Canal Bridges.jpg
As part of the design and construction of the Barge Canal in the first two decades of the 20th century, it was deemed that the U & MV by-pass bridge over the Mohawk River was incompatible and would need to be removed. This was legally contested and went as far as the State Attorney General in Albany. The U & MV lost the fight and was required to us a new set of bridges, roughly on the alignment of the U & MV local line parallel with Mohawk St. The new railway bridge was built (after more legal contests) as part of the new single concrete project involving the Mohawk St bridge, guard-gate, waste weir and dam to be located at the point where the Barge Canal would enter a land cut going east, separate from the Mohawk River.
However, at this time there was no connection between the grade-separated WS and the U & MV street line. This arrangement left the double-track by-pass terminated on the Mohawk side of the Mohawk River, with the only connection to the Herkimer-to-Little Falls section being the single-track street line through Ilion and Mohawk. Unable to convince the village boards to allow rerouting of the “big cars” down their main streets, or financially unwilling to build yet another, higher bridge across the Mohawk, the U & MV turned to the Oneonta & Mohawk Valley, predecessor to the Southern New York Power and Railway(1916)/Southern New York Railroad(1924), which had reached an agreement with the West Shore to install a freight connection in Mohawk. From the Utica Observer, Friday, January 14, 1910:
"DREAM OF BIG CARS HAS FADED. Interurban Electrics Will Still Use the Cut-Off. Clever Arrangement Has Been Made by the Company at Mohawk to Use(sic) When Barge Canal Breaks in on the Line...proposed route of the Barge Canal would compel the railroad company to discontinue using the cut-off below Mohawk...they would have to run the big cars through Ilion...evidently the railroad company does not intend to use the old [Mains St.] route if it can be avoided, and here is the way it is done: ...the Oneonta & Mohawk Valley RR, which currently uses the tracks of the U. & M. V. through Mohawk to Herkimer ...made arrangements whereby a siding connecting the tracks of the U. & M. V. with the West Shore at the point where the latter road passes under the West Shore tracks was to be put in. This was to be done for the purpose of handling freight. The West Shore station at this point was moved and the new siding placed in position. Now comes the news that the U. & M. V. will not run the large cars through Ilion and Mohawk, as expected, but will run them over the West Shore to the Mohawk Station, and then by means of the new siding connect with their own tracks at this point and so over to Herkimer."
The following photo, taken from the hillside south of the WS Mohawk passenger station, shown the resulting complex of bridge structures.
8 East End 1914 Bird's Eye.jpg
The bridges in the above photo are as follows:
1. WSRR bridge over E. Main St. (Mohawk)/Mohawk St.(Herkimer), original street-route of single-track U&MV local traffic, similarity to (4) suggests it may be new construction.
2. New WSRR bridge over rerouted U&MV, beginning of new U&MV double-track
3. Older Whipple truss bridge of Mohawk St. over original Erie Canal
4. New double-track U&MV bridge over original Erie Canal
5. New Mohawk St. bridge over Barge Canal
6. New Guard Gates for Barge Canal, allow draining for maintenance and protection during flooding of Mohawk River
7. New double-track, double-span U&MV bridge over Barge Canal
8. Original U&MY by-pass double-track bridge over Mohawk River
9. Older Mohawk St. bridge over Mohawk River
10. Original single-track U&MV bridge over Mohawk River, may have been structurally joined to side of (9)
11. New waste weir in Mohawk River for maintaining pool elevation for combined Barge Canal/Mohawk River upstream (left) of here
12. New double-track U&MV bridge over Mohawk River, an early, primitive Poire’e dam was constructed just east (right) of here, later replaced by current movable dam
13. Location of prior concrete culvert U&MY approach to original by-pass Mohawk River bridge, partially removed for new Barge Canal channel
14. Probable connection from WSRR to U&MV, required relocation of WSRR passenger station from south side to north side of mainline
This would place the effective connection with the West Shore somewhere opposite the freight house. (Location 43.014N x -74.99W) Supporting this assertion is a section of curving track visible in the foreground of the 1914 Bird’s Eye View image above that leads to no known industry. In addition, Sanborn Maps from 1902 (before the Barge Canal) and 1910 (after construction began) show the passenger station relocated as per the newspaper article. These maps show the station was literally moved across the tracks, not turned, and that the ticket office was now facing the river instead of the railroad – not that they were selling all that many tickets by then. This would have created what amounted to a short double switchback to move a trolley car from Ilion to Herkimer.
3rd Section to follow in separate post
- WestShore4Ever
You do not have the required permissions to view the files attached to this post.