by lirr42
Yeah, they probably had a bunch of M8's sitting in GCT that they couldn't send out on the NHL so they probably sent a set or two out on the H&H just to relieve some congestion.
Railroad Forums
Moderators: GirlOnTheTrain, nomis, FL9AC, Jeff Smith
lirr42 wrote:Yeah, they probably had a bunch of M8's sitting in GCT that they couldn't send out on the NHL so they probably sent a set or two out on the H&H just to relieve some congestion.Yes, that was my theory (see my post, above.)
RearOfSignal wrote:You'll probably see M8's all over the H&H for a while, had some in NWP already.I almost rode an M8 this morning. But it turned out it was a local (running 10 minutes late), the express (also ~10 minutes late) was an M7a .
lirr42 wrote:Yeah, they probably had a bunch of M8's sitting in GCT that they couldn't send out on the NHL so they probably sent a set or two out on the H&H just to relieve some congestion.No so much to relieve congestion, there's not much coming down the NHL anyway. But GCT is limited in its abilities to service equipment, so that stuff gets sent out. The Harlem will probably see the through trains to Wassaic replaced by electrics south of Southeast. There was a scramble to free up electrics this morning to cover some of the normal bomb train runs. So we might see M8s in unusual places for a while.
Jeff Smith wrote:News of the additional option came to me through this thread; I didn't know there was one AFTER the 380 and 25 singles... That's a pretty big fleet considering where they were. Sounds like they'll have more than enough now for SLE and PSAS (if the latter ever happens).The NHL is so car-hungry that they'd be best off just exhausting the order altogether PSAS's status be damned. Over the rated lifetime of these things before first rebuild the vehicle requirements are going to swell so much that ultimately the current growth curve is going to merit all 458 units. East-of-Stamford consists are going to have to get a lot longer. Many platforms that are currently 4-6 cars are going to have to get lengthened through gradual station overturning to 8-10 cars to keep the dwell times from decaying. Maxing the order is the only way to effectively feed the beast, lest they find themselves in such an acute pinch that a workalike supplemental order has to go on the table in 10 years. They save money in the long run getting it over with now.
How many are they churning out a week? 4? 8? if it's 4, they'll be done in 30 weeks with the initial order. 8 would be 15. Then they'll work on the singles and additional options; the singles would take about 6 weeks. Another possible 58 cars at 4 per week would be 15 weeks or less. So at 4 per week (and I think it's more) we're talking they'll be done through the singles as early as back of the pad calculation 9 months, or next summer. If you go with 8 per week, we're talking next spring. An additional 58, you'd still be done by the end of the year 2014 I think. And then on to the M9's...